Due to the improper operation of low temperature chiller system, there is the possibility of water entering into refrigerant system. Therefore, in view of the problem of water supply in low temperature chiller system, process guidance is formulated to serve as a reference for maintenance.
1. Analyse the reasons. Check the whole low temperature chiller system to confirm the cause of freezing damage and find out the leak point.
2. Blow dirt in sections.
(1) First, air compressor can be used to blow water (save nitrogen), until no water mist precipitate. Then blow with high pressure nitrogen, at the same time, heat the nitrogen (the nitrogen cylinder is prohibited from heating).
(2) Because the pipeline of low temperature chiller system is complex, water can be blown out in segments by using welding torch in some parts according to specific conditions.
(3) Heat and dry. The capillary, thermal expansion valve, compressor and other small components can be placed in the oven to bake and dry. Do replace the refrigerating oil in the compressor after the water is dried.
1. Vacuum drying
(1) Restore the pipeline and maintain the nitrogen pressure to ensure the air tightness of the system. Then connect the vacuum pump to the system for vacuum drying. (Dry filter barrel should be added to the front end of vacuum pump to avoid excessive water and gas entering the vacuum pump)
(2) In the process of vacuum drying, heat the place where water is easily stored in the pipeline, and the time can be determined according to the site.
2. Debugging and running.
(1) Make sure that the water in the system is basically removed.
(2) Connect the external drying filter barrel to the system and replace the desiccant after running for 5 minutes. At the same time, observe the operating parameters of the unit and pay attention to the sound of the compressor. If the dry filter is cold, the expansion valve frosts, and there is a pressure difference of more than 0.5 kg before and after the return air filter, stop the compressor immediately.
3. Completion of maintenance
(1) Remove the refrigerant pipe from the drying filter barrel and restore it.
(2) Check the supplementary refrigerant quantity. Turn on and check the machine running parameters to confirm normal.
Recommandations connexes
-
Invitation Letter | 10.17-19 Nanjing International Expo Center [5G18]
1344Our company will participate in the 81st APIChina China International Pharmaceutical Raw Material Intermediate Packaging Equipment Exhibition held at Nanjing International Expo Center from October 17-19, 2018. At that time, we will exhibit refrige...
Voir les détails -
What is the principle of industrial air-cooled chillers
1599Many industrial productions are inseparablefrom the low-temperature production environment provided by the chiller andcannot obtain efficient production capacity. Therefore, industrial chillerequipment is a very important refrigeration equipmen...
Voir les détails -
Principe de fonctionnement des refroidisseurs d'air industriels LNEYA
1070L'aéroréfrigérant industriel est un échangeur de chaleur qui utilise l'air pour refroidir le fluide chaud. Le fluide chaud dans le tube est chauffé par l'échange de chaleur entre la paroi du tube, l'ailette et l'air extérieur, qui est généralement fourni par le ventilateur. Notre I...
Voir les détails -
Analyse de l'entretien du circulateur basse température dans la vie quotidienne
1117Guanya is a leading role in heating cooling circulator. It provides the customers with proposal and technology of controlling the cold and heat, temperature control system with stable property, extending the service life of heating cooling circula...
Voir les détails